NJ Facility Owner Guide

NJDEP Air Permitting Guide

Preconstruction permits, Title V Operating Permits, General Permits, and annual Emission Statements — what triggers each, how long they take, and where facilities most often get tripped up in New Jersey.

  • 100% lender approval on Phase I ESAs
  • 1-week priority Phase I turnaround
  • Fixed-fee, same-day quotes

Free scoping call — fixed-fee quote with the scope locked before we start.

The four NJDEP air permit tracks

NJDEP's Bureau of Air Permits runs four parallel tracks under N.J.A.C. 7:27: General Permits for common equipment, source-specific preconstruction permits (Permit to Construct / Certificate to Operate) for larger or non-standard sources, Title V Operating Permits for major sources, and annual Emission Statements for reportable facilities. Most projects touch at least two of these. Envicon's NJ Air Permitting practice manages all four end-to-end.

Common triggers

  • New boiler, furnace, or process heater above 1 MMBtu/hr input
  • Emergency or standby generator over 37 kW (approximately 50 hp)
  • New or modified spray booth, coating line, or printing press
  • Storage tank changes affecting VOC or HAP throughput
  • Manufacturing process changes that raise potential-to-emit
  • Facility becoming a major source (Title V applicability change)

How the process runs

  1. Step 1
    Applicability Determination

    Confirm which subchapters apply — 7:27-8 (preconstruction), 7:27-19 (NOx control), 7:27-22 (Title V), plus federal NSPS/NESHAP overlays. Envicon issues a written applicability memo before any filing.

  2. Step 2
    Emissions Inventory & Modeling

    Quantify potential-to-emit (PTE) for each source, apply AP-42 or manufacturer factors, and run AERSCREEN/AERMOD dispersion modeling where State-of-the-Art (SOTA) or risk screening is triggered.

  3. Step 3
    Permit Application

    Prepare and submit through NJDEP's RADIUS software or NJDEP Online — including equipment inventory, control device specifications, monitoring plan, and Compliance Plan narrative.

  4. Step 4
    Public Notice & Draft Permit

    Title V and significant modifications require a 30-day public comment period and EPA 45-day review before the final permit issues.

  5. Step 5
    Certificate to Operate & Ongoing Compliance

    Once issued, track recordkeeping, semi-annual monitoring reports, deviation reports, annual compliance certifications, and Emission Statement filings.