BICC Cables Site DCU Area 2B Sediment Remediation

Yonkers, New York8 monthsConfidential

Innovative sediment remediation for a 17-acre Hudson River waterfront site under the NYSDEC Brownfield Cleanup Program, resolving PCB contamination after six previous unsuccessful remediation attempts.

Project Overview

The Former BICC Cables Site is a 17-acre property located along the Hudson River in Yonkers, Westchester County, New York. Polychlorinated Biphenyl (PCB) contamination of Hudson River sediments beneath the Electronic Power Research Institute (EPRI) Building required remediation under the NYSDEC Brownfield Cleanup Program. The NYSDEC Record of Decision (ROD) prescribed sediment excavation and removal as the Selected Remedy for Dredge Certification Unit (DCU) Area 2B, a 24,500-square-foot underwater area.

The Challenge

Since 2010, six previous attempts to comply with the ROD Selected Remedy had failed due to unmanageable debris beneath the building, excessive turbidity, and soft sediments that trapped heavy equipment. In 2013, Remote-Controlled Robotic Vacuum dredging (ScanCrawler) could not achieve NYSDEC-approved productivity rates due to limited visibility, loose debris, and unsafe deployment conditions. NYSDEC requested an Alternatives Analysis Report for selection of the final remedy.

Our Solution

Envicon's team designed a multi-layer engineered Reactive Core Mat Sediment Cover System (SCS Remedy) as the optimal solution for completing remediation of DCU Area 2B. This innovative approach received NYSDEC approval in February 2014 and was successfully implemented in summer 2014, overcoming the technical and economic challenges that had defeated six prior remediation methodologies.

Key Highlights

  • Designed innovative multi-layer Reactive Core Mat Sediment Cover System
  • Prepared Alternatives Analysis Report after six failed remediation attempts
  • Obtained NYSDEC approval for SCS Remedy in February 2014
  • Remediated 24,500-square-foot DCU Area 2B underwater sediments
  • Addressed PCB contamination beneath EPRI Building structure

Results Achieved

  • Overcame six previous unsuccessful remediation attempts dating to 2010
  • Achieved NYSDEC Brownfield Cleanup Program compliance
  • Successfully implemented innovative Sediment Cover System remedy
  • Completed remediation of 17-acre Hudson River waterfront site

Project Details

Client

Confidential

Location

Yonkers, New York

Duration

8 months

Scope

Sediment Cover System remediation for PCB-impacted Hudson River sediments under NYSDEC Brownfield Cleanup Program

Services Provided

Remedial Design
Alternatives Analysis
NYSDEC Brownfield Cleanup Program
Sediment Cover System Design
Reactive Core Mat Installation
PCB Remediation
Remedial Action Workplan
Regulatory Coordination
Construction Oversight

Share this case study

Transparent pricing for Site Remediation & Brownfield Redevelopment

Answer a few questions about your property and get a real price range in under 2 minutes. No sales call required.

  • Site-specific range
  • Under 2 minutes
  • No obligation
  • Emailed to you

Preliminary estimate only. Not an engineering quote.

FAQ

BICC Cables Site DCU Area 2B Sediment Remediation — Frequently Asked Questions

Common questions about the scope, challenges, and outcomes of this Yonkers, New York case study.

Have a Similar remediation? Get a Free Quote

100% lender approval across 350+ Phase I ESAs · 21+ years in the NY/NJ metro market. Same-business-day scoping for NY & NJ owners, lenders, and developers.

Request a Quote for Your Site

Tell us about the property and we'll come back the same business day with scope, schedule, and fee.

Project location

Type at least three characters to see address suggestions, then use the arrow keys to choose one.

Your information is confidential and routed only to our licensed project team.

Protected by reCAPTCHA — this site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.

Call Now