Harrison MGP Site – PATH Substation IRM
Remedial action oversight for site preparation of a future PATH electric substation, including below-grade excavation, dewatering treatment, and installation of geosynthetic liner and clean cap.
Project Overview
The Harrison MGP Site IRM supported site preparation for a future electric substation serving the PATH rail network. Excavation required work below the groundwater table near the Passaic River, where dewatering was restricted by downstream sewer capacity. Prior investigations identified elevated lead concentrations, requiring continuous in-situ waste classification and stabilization.
The Challenge
Excavation below the groundwater table near the Passaic River with limited dewatering capacity due to downstream sewer restrictions. Elevated lead concentrations required careful waste classification and in-situ stabilization.
Our Solution
Envicon's team sequenced below-grade excavation to minimize dewatering requirements, performed in-situ waste classification for materials with elevated lead, developed a comprehensive NJDEP-approved soil reuse plan, and managed dewatering treatment and GCL installation.
Key Highlights
- Sequenced below-grade excavation to minimize dewatering
- Performed in-situ waste classification for lead-impacted materials
- Developed NJDEP-approved soil reuse plan
- Oversaw well abandonment and gas holder removal
- Managed dewatering treatment and GCL + clean cap installation
Results Achieved
- Delivered compliant substation footprint preparation
- Achieved regulatory approval for soil reuse
- Minimized dewatering volumes and costs
- Enabled future PATH infrastructure construction
Project Details
Client
Confidential
Location
Harrison, New Jersey
Duration
12 months
Scope
Remedial action oversight for PATH substation site preparation
Services Provided
Share this case study
Related Services



You May Also Need
Dewatering
Matches “oversight” scope
Construction dewatering system design, permitting, and field oversight for NJ and NY sites.
Grant & Funding Support
Matches “remediation” scope
Grant identification, application preparation, and reimbursement documentation for brownfield, remediation, and resiliency funding programs.
Compliance Audit
Matches “environmental” scope
Standard and pre-inspection compliance audits plus annual compliance programs.
Health & Safety Plans
Matches “remediation” scope
Site-specific HASPs, HAZWOPER compliance documentation, and field safety oversight for investigation, remediation, and construction work.
Where We Work Nearby
Harrison MGP Site – PATH Substation IRM — Frequently Asked Questions
Common questions about the scope, challenges, and outcomes of this Harrison, New Jersey case study.
Similar Projects
Have a Similar remediation? Get a Free Quote
100% lender approval across 350+ Phase I ESAs · 21+ years in the NY/NJ metro market. Same-business-day scoping for NY & NJ owners, lenders, and developers.
Request a Quote for Your Site
Tell us about the property and we'll come back the same business day with scope, schedule, and fee.