Newark Prudential Office Complex Construction
Site remediation and LSRP services for fast-track construction of a 26-story office building and parking garage on a 2.7-acre downtown Newark city block.

Project Overview
Envicon's team provided site remediation and LSRP services to support the fast-track construction of a new 26-story office building and parking garage for SJP Properties. The 2.7-acre project site encompasses an entire city block located within the downtown section of Newark. The task was to provide site remediation and geotechnical monitoring services synchronized with an expedited construction schedule.
The Challenge
The project site was conflicted by immediately adjacent structures, very old utilities, and neighboring land uses. Three on-site buildings required demolition and contained hazardous materials. Initial site studies indicated several zones of contaminated materials and free product as deep as 32 feet below the existing ground surface.
Our Solution
Working with the project developer and construction manager, Envicon's team performed and submitted expedited remedial investigations and remedial action work plans. The remedial work was divided into phases keyed to the demolition of on-site buildings. Nine underground storage tanks were removed. A GPS-enabled Fuel Fluorescence Detection (FFD) technique was used to specifically delineate the limits of floating product and contaminated soil layers. A 3D model was constructed using FFD and other site investigation results, enabling removal of floating product before excavation and minimizing the volume of soils requiring remediation, resulting in significant cost savings. Envicon's team provided an on-site environmental monitor who operated a perimeter air monitoring system and worked with the contractor and construction manager during remedial construction.
Key Highlights
- Supported fast-track construction of 26-story office building
- Performed expedited remedial investigations and RAWPs synchronized with construction
- Removed nine underground storage tanks from the site
- Deployed GPS-enabled Fuel Fluorescence Detection (FFD) technology
- Constructed 3D contamination model for precision excavation
- Provided on-site environmental monitor with perimeter air monitoring system
Results Achieved
- Achieved significant cost savings through precision contamination delineation
- Removed floating product before excavation minimizing soil removal volumes
- Maintained expedited construction schedule despite complex contamination
- Successfully remediated contamination extending 32 feet below grade
Project Details
Client
SJP Properties
Location
Newark, New Jersey
Duration
12 months
Scope
Site remediation and LSRP services for 2.7-acre downtown Newark office complex construction
Services Provided
Share this case study
Related Services



You May Also Need
Community Air Monitoring
Matches “work” scope
NYSDOH Generic CAMP preparation and real-time perimeter particulate and VOC monitoring during intrusive site work.
Health & Safety Plans
Matches “remediation” scope
Site-specific HASPs, HAZWOPER compliance documentation, and field safety oversight for investigation, remediation, and construction work.
NYSDEC BCP
Matches “remedial” scope
BCP application, remedial investigation, RAWP implementation, and Certificate of Completion support for New York brownfield sites.
Phase II ESA
Matches “environmental” scope
Subsurface investigation of soil, groundwater, and soil gas to NJDEP and NYSDEC protocols following a Phase I REC.
Where We Work Nearby
Industries We Serve
Services Available in This Market
Newark Prudential Office Complex Construction — Frequently Asked Questions
Common questions about the scope, challenges, and outcomes of this Newark, New Jersey case study.
Similar Projects
Have a Similar remediation? Get a Free Quote
100% lender approval across 350+ Phase I ESAs · 21+ years in the NY/NJ metro market. Same-business-day scoping for NY & NJ owners, lenders, and developers.
Request a Quote for Your Site
Tell us about the property and we'll come back the same business day with scope, schedule, and fee.