Southwest Brooklyn Marine Transfer Station
Design-during-construction and resident engineer support services for a $150 million pile-supported marine transfer station with 700-900 ton daily capacity, providing project management, multi-agency permit coordination, and design change management.

Project Overview
The Southwest Brooklyn Marine Transfer Station is a $150 million, first-of-its-kind solid waste infrastructure facility located near Coney Island. Constructed on an existing Sanitation Garage property adjacent to a local marina and community fishing waters, the pile-supported structure is framed in high-strength structural steel to accommodate heavy floor loads and long, column-free spans required for waste dumping, processing, and container handling operations. Envicon team members provided comprehensive design-during-construction and resident engineer support services, applying lessons learned from the prior Hamilton Marine Transfer Station project to streamline permit coordination and design change management.
The Challenge
The project required coordinating permit preparation across multiple NYC agencies including DOB, FDNY, SBS, and NYCDEP while managing complex design changes in a harsh marine environment. The pile-supported structure with cast-in-place concrete box girder ramps demanded precise coordination between design teams and field construction. Additionally, the waterfront location required particular attention to protecting the bay waters used by the community for fishing and recreation.
Our Solution
Envicon team members provided project management and design-during-construction services, leveraging lessons learned from the Hamilton MTS construction project to anticipate and resolve design change issues before they impacted the schedule. The team coordinated DOB, FDNY, SBS, and NYCDEP permit preparation and submission, ensuring regulatory approvals kept pace with construction milestones. Envicon team members maintained continuous field presence to review construction activities, verify design compliance, and coordinate real-time design clarifications with the engineering team.
Key Highlights
- Provided design-during-construction and resident engineer support for $150 million facility
- Coordinated DOB, FDNY, SBS, and NYCDEP permit preparation and approvals
- Applied lessons learned from Hamilton MTS to streamline design change coordination
- Supported construction of pile-supported structure with high-strength structural steel framing
- Managed design clarifications for cast-in-place concrete box girder ramp construction
- Maintained field coordination for waterfront construction protecting community bay waters
Results Achieved
- Facility processes 700-900 tons of municipal solid waste daily
- Contributes to 60+ million mile annual reduction in truck traffic citywide
- Supports 34,000 ton annual reduction in greenhouse gas emissions
- First solid waste infrastructure designed for future recycling technologies
- Multi-agency permit coordination achieved without construction delays
Project Details
Client
DSNY/DDC
Location
Brooklyn, New York
Duration
48 months
Scope
Design-during-construction services, resident engineer support, project management, and multi-agency permit coordination for marine transfer station construction
Services Provided
Share this case study
Related Services



You May Also Need
Dewatering
Matches “design” scope
Construction dewatering system design, permitting, and field oversight for NJ and NY sites.
NYC Permit Expediting
Matches “dob” scope
DOB, DEP, DOT, OER, FDNY, and Parks filing strategy, objection resolution, and approvals tracking for NYC projects.
Stormwater & SWPPP
Matches “construction” scope
Stormwater pollution prevention plans, permitting, and post-construction stormwater compliance.
Construction Management
Matches “construction” scope
Owner-side construction management, resident engineering, cost and schedule control, and closeout documentation.
Where We Work Nearby
Industries We Serve
Services Available in This Market
Southwest Brooklyn Marine Transfer Station — Frequently Asked Questions
Common questions about the scope, challenges, and outcomes of this Brooklyn, New York case study.
Similar Projects
Have a Similar environmental? Get a Free Quote
100% lender approval across 350+ Phase I ESAs · 21+ years in the NY/NJ metro market. Same-business-day scoping for NY & NJ owners, lenders, and developers.
Request a Quote for Your Site
Tell us about the property and we'll come back the same business day with scope, schedule, and fee.