NHSA Treatment Plant Upgrade Projects

Hoboken, NJ14 monthsNHSA

Construction phase management for wastewater facility improvements including siphon sewer relining, PURAC filtration upgrades, and major switchgear replacement while maintaining continuous plant operations.

Project Overview

The NHSA Treatment Plant Upgrade Program included a series of wastewater facility improvement projects across two treatment plant locations in Hoboken. Work involved construction phase project management for a siphon sewer pipe relining project, a PURAC filtration system control room upgrade, and major switchgear replacement activities.

The Challenge

The upgrades required close coordination among NHSA, contractors, and municipal authorities while maintaining continuous plant operations throughout construction.

Our Solution

Envicon's team managed day-to-day construction, field coordination, and oversight of resident engineering staff and general contractors. The team prepared and administered contractor bid packages, coordinated street closures, and led change order preparation and negotiation.

Key Highlights

  • Managed construction oversight and resident engineering staff
  • Prepared and administered contractor bid packages
  • Coordinated street closures with local municipalities
  • Led change order preparation and negotiation
  • Maintained continuous plant operations throughout construction

Results Achieved

  • Completed facility upgrades without operational disruption
  • Improved treatment performance and system reliability
  • Achieved regulatory compliance across critical infrastructure
  • Streamlined contractor coordination and approvals

Project Details

Client

NHSA

Location

Hoboken, NJ

Duration

14 months

Scope

Construction management for wastewater treatment plant upgrades

Services Provided

Construction Management
Civil Engineering
Wastewater Facility Upgrades
Bid Administration
Field Coordination

Share this case study

Transparent pricing for Civil & Geotechnical Engineering

Answer a few questions about your property and get a real price range in under 2 minutes. No sales call required.

  • Site-specific range
  • Under 2 minutes
  • No obligation
  • Emailed to you

Preliminary estimate only. Not an engineering quote.

FAQ

NHSA Treatment Plant Upgrade Projects — Frequently Asked Questions

Common questions about the scope, challenges, and outcomes of this Hoboken, NJ case study.

Have a Similar civil? Get a Free Quote

100% lender approval across 350+ Phase I ESAs · 21+ years in the NY/NJ metro market. Same-business-day scoping for NY & NJ owners, lenders, and developers.

Request a Quote for Your Site

Tell us about the property and we'll come back the same business day with scope, schedule, and fee.

Project location

Type at least three characters to see address suggestions, then use the arrow keys to choose one.

Your information is confidential and routed only to our licensed project team.

Protected by reCAPTCHA — this site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.

Call Now